Progress on Uskmouth Battery Energy Storage Systems
The Uskmouth Sustainable Energy Park is advancing with the development of two significant battery energy storage systems, AW1 and AW2, aimed at enhancing energy storage capacity in Wales.
Overview of Uskmouth Sustainable Energy Park
The Uskmouth Sustainable Energy Park (USEP) in Wales is witnessing significant advancements with the development of two battery energy storage systems (BESS) — AW1 and AW2. These projects are poised to enhance the region's energy storage capabilities and contribute to the UK's renewable energy goals.
AW1 Project Details
Ampeak Energy has commenced construction on the first project, AW1, which has a capacity of 120 MW and can store up to 240 MWh of energy. The construction of AW1 began in October 2026, with a target to connect to the grid in the first quarter of 2027. The local construction firm, Jones Bros, is responsible for the build, while Canadian Solar is supplying the BESS units. This project is expected to play a crucial role in stabilising the grid and supporting renewable energy sources.
AW2 Project Progress
The second project, AW2, is a joint venture between Ampeak Energy and Econergy International. Recently, Ampeak Energy secured planning permission from Newport City Council for AW2, which will have a capacity of 250 MW and is designed to offer up to five hours of energy storage duration. Notably, the planning approval includes the removal of 140,000 tonnes of historic pulverised stored ash from the site, which is a significant environmental consideration.
Financial Aspects and Timeline
Ampeak Energy acquired complete ownership of the AW1 project for £299,000 in August 2024. For the AW2 project, construction is anticipated to begin following the completion of the AW1 project, with a potential capacity expansion of up to 1 GWh. The AW2 project is expected to further enhance the energy storage capabilities at the Uskmouth site, which can support approximately 3.5 GWh of battery storage projects overall.
Future Outlook
As the energy landscape continues to evolve, the developments at Uskmouth are crucial for meeting the UK's energy storage needs. The successful implementation of these BESS projects will not only contribute to energy resilience but also support the transition towards a more sustainable energy future. Stakeholders in the energy sector are keenly observing the progress of these projects, which are set to play a pivotal role in the region's energy strategy.
Industry sources
This story was synthesised from the following publishers.
Related coverage
- Projects & InfrastructureSizewell C Tunnel Segment Factory Approved in BristolA new tunnel production facility for Sizewell C has been approved in Avonmouth, promising to create hundreds of jobs and support the construction of marine tunnels for the nuclear power plant.
- Projects & InfrastructureUnited Infrastructure Joins BEAMA to Propel Electricity Network InvestmentUnited Infrastructure has become a full member of BEAMA, aligning with the Electricity Networks Sector Growth Plan aimed at substantial investment in the UK’s electricity infrastructure.
- Projects & InfrastructureTeesside to Host UK's Largest Electricity SubstationNational Grid Electricity Transmission is set to build the UK's largest electricity substation in Teesside, supporting a major AI data centre project.